Construction Updates

AmaresaAmenities-1506_small.jpg

CONSTRUCTION UPDATES

  • Road Construction:
    - Phase 1 to 5 : 100% Completed
  • Gate and Guardhouse: Completed last December 2014
  • Deep Well and Water Tank
    - Completed and fully operational since October 2015
    - Source of water supply for Sentrina homeowners.
  • Power Facilities
    - Phase 1 & 2: Energized and operational since October 2015
    - Phase 3 & 4: Energized and operational since June 2016
    - Streetlights: Operational last December 2015
  • Linear Park: 100% Completed last  May 2016 ( Blk 3 and 4 area)
  • Basketball Court:  100% Completed last May 2018
  • Clubhouse & Swimming Pool : 100% Completed last May 2018